County A - STH 76 to STH 47

Print
Press Enter to show all options, press Tab go to next option
 Please check back often. Updates may be made on a frequent basis.

 

CTH A - Mayflower Rd to 47 - Reconstruction is scheduled to start the first week of July and completion is anticipated in early October, 2019.

Highway will be closed to through traffic. Detour will be WIS 76 and CTH S.

 

Project Description

Reconstruction of CTH A from Mayflower Road to STH 47. Work items consisting of Base Aggregate, Culvert Pipes, Curb & Gutter, Erosion Control, Grading, HMA Pavement, Landscape Restoration, Pavement Marking, Signage, & Other Incidental Items.

Project Status

Peters Concrete is expected to start reconstruction the first week of July and completion is anticipated early October, 2019.  Road Closed to through traffic.

7/29 week's work:  Continued Excavation Common and grading of new subgrade for roadway and ditches on County Road A starting at State Road to moving West.  Continued placing Base Aggregate Dense 1 ¼ Inch on County Road A from ¼ mile West of State Highway 47 and State Road.  Spread Salvaged Topsoil on ditches along County Road A from ¼ mile West of STH 47 to State Road.

8/4 week's work: Continue Excavation Common and grading of new subgrade for roadway and ditches on County Road A from RR Crossing (1/10 mile West of State Road) to Hample Road.  Continue placing Base Aggregate Dense 1 ¼ Inch on County Road A from State Road to Hample Road.

Aug 26 week’s work: Continue Excavation Common and grading of new subgrade for roadway and ditches on County Road A starting ½ mile west of Hample Road to Mayflower Road.  Continue placing Base Aggregate Dense 1 ¼ Inch on County Road A starting ½ mi west of Hample Road to Mayflower Road. Remove existing culvert pipes and installing new culvert pipes at state road intersection and driveways throughout project. 

Sept. 3rd week’s work: Finish Excavation Common and grading of new subgrade for roadway and ditches on County Road A from Mayflower Road to ½ mi West of Hample Road.  Continue placing Base Aggregate Dense 1 ¼ Inch on County Road A.  Installing culverts under CTH A.  Move grading operations to East end of project.

Sept. 9th week’s work: Finish Excavation Common and grading of new subgrade for roadway and ditches on County Road A 1/4 mile west of STH 47 to STH 47.  Finish Grading Base Aggregate Dense 1 ¼ Inch along entire project to prepare for asphalt paving the week of September 16.

Sept. 16th week’s work: Continue shaping ditches and spreading topsoil throughout the project.  Place asphaltic pavement on project.

 

Project Contacts:

Contractor

Signing Contractor

Alternate Contact:

Duke Peters, Peters Concrete

920-621-1709

Barricade Flasher Service

920-398-2990

Outagamie County Highway Department

920-832-5673

highwayemail@outagamie.org

 

:  

CTH A - 76 to Mayflower Rd - Scheduled for reconstruction in 2020.

A - 76 to Mayflower Plans

A - Mayflower to 47 draft 90% plans for Co Web Site

A - 76 to Mayflower 2017 06 19 Plat

A - Mayflower to 47 Plat 12-11-17

Public Informational Meeting - Held on June 22, 2016

 

Proposed Detour Plan

 