County Highway Construction and Paving Project Updates as of 03/06/2019

A

STH 76 to STH 47

Towns of Black Creek & Bovina

Project Description

The highway is in need of wider paved lanes, paved shoulders, and flatter ditch slopes to meet current County highway design and safety standards.

Project Status

·         Mayflower Rd to STH 47 – Construction planned for 2019

·         STH 76 to Mayflower Rd – Construction planned for 2020

Traffic Impacts

Highway will be closed to through traffic.  Detour planned to be Hwy 76 and CTH S.

More Information

Capital Improvement Program

CTH A Webpage

 

A

CTH OO to Capitol Drive

Town of Grand Chute

Project Description

Improve existing asphaltic surface by profile milling and installing a new asphalt overlay.

Project Status

Repaving planned for 2019.

Traffic Impacts

Highway will be restricted to 1 lane in each direction when milling and paving is taking place.

More Information

Capital Improvement Program

 

 

CA

CTH CB to Mall Drive

Towns of Grand Chute & Greenville

Project Description

The highway will be reconstructed as a 4-lane divided urban highway with curb & gutter on both the median shoulder and outside shoulder.  Multi-lane Roundabouts are planned at the intersections of Mayflower Drive and at McCarthy Road to improve operations and safety. A multi-use trail will be constructed on the north side of the highway, and sidewalks and pedestrian crossings of CTH CA are planned at the roundabouts.

Project Status

Right-of-way acquisition in 2019.

Reconstruction in 2020.

Traffic Impacts

Portions of the highway will be closed during construction. The signed detour route will be I-41, Highway 96, and County CB.  Construction planned for 2020.

More Information

Capital Improvement Program

CTH CA Webpage

 

 

CB

& Atlantis Intersection (north of CTH CA)

Town of Greenville

Project Description

Construct a multi-lane roundabout at the intersection of County CB & Atlantis Drive.  Also realign Discovery Drive intersection to Atlantis Drive.

Project Status

Construction in 2019.  Planned from July to October.

Traffic Impacts

Project will be built in two phases.  Phase 1 will be the internal airport street network for Discovery Drive and Atlantis Drive.  Phase 2 will be the County CB & Atlantis intersection. County CB will be closed to through traffic during Phase 2.  The signed detour for County CB will be County CA, I-41, and Highway 96.

More Information

Capital Improvement Program

CTH CB Webpage

 

 

CE

& Railroad Street Intersection

Village of Kimberly

Project Description

Traffic study, design, and future reconstruction of the intersection. Several alternatives are being considered, including traffic signals, roundabout and unique alternatives that have restrictions to cross traffic.

Project Status

Conceptual alternatives were presented to Kimberly Planning Commission in December 2018.  Preliminary plans and a full public informational meeting is planned in Spring 2019.  Reconstruction may be as early as 2021.

Traffic Impacts

Pending

More Information

County CE & Railroad Street Webpage

 

 

CE

& CTH N Interchange Improvements

Town of Buchanan

Project Description

Traffic signals will be installed at both ramp intersections.

Project Status

Planned for Summer 2019

Traffic Impacts

County N will be reduced to 1 lane in each direction during project work.  Daytime closures of the westbound off ramp may be required during portions of the project.

More Information

Capital Improvement Program

 

 

 

CE

and CTH K (Buchanan Rd) Intersection

Town of Buchanan

Project Description

Study and design of intersection improvements

Project Status

The median was closed to cross traffic in May 2018.  The Highway Dept has been studying the impacts the median closure has on safety and operations.  No crashes have occurred at the intersection, and no new operational issues have been discovered at key adjacent intersections.

The County continues to work with the Village of Combined Locks and Town of Buchanan regarding the future of the intersection.  The speed limit along County CE is also being studied.

Traffic Impacts

County CE Traffic can make a right turn onto Buchanan Road, and Buchanan Road traffic can make a right turn onto County CE.  All Buchanan Road cross movements are restricted.

More Information

Capital Improvement Program

 

 

 

CE

STH 55 to Outagamie Rd

Town of Buchanan, City of Kaukauna

Project Description

Improve existing asphaltic surface by pulverizing existing pavement, regrading stone base and installing a new asphalt surface. Spot improvements are planned for traffic operations and safety.

Project Status

Repaving planned for 2019.

Traffic Impacts

The highway will be closed to through traffic. The signed detour route will likely be Highway 55, County KK, and County D in Brown County

More Information

Capital Improvement Program

 

 

 

D

West County Line to CTH F

Town of Deer Creek

Project Description

Improve existing asphaltic surface by paving a leveling course and a new asphalt overlay.

Project Status

Repaving planned for 2019.

Traffic Impacts

Highway will remain open with daytime flagging operations during construction.

More Information

Capital Improvement Program

 

 

EE

(Ballard Rd)

CTH O to CTH S

Center, Freedom

Project Description

Improve existing asphaltic surface by pulverizing the pavement, regrading the stone base, and paving a new asphaltic surface

Project Status

Planned for 2019.

Traffic Impacts

Highway will be closed to through traffic.  Detour expected to be County E, County C, and County S.

More Information

Capital Improvement Program

 

 

 

GV

and McCarthy Rd Intersection

Grand Chute

Project Description

Construction of a roundabout

Project Status

Planned for 2019.

Traffic Impacts

County GV will be closed to traffic. Detour expected to be Highway 96 and County CB.

More Information

Capital Improvement Program

 

 

 

I

CTH F to North County Line

Maine

Project Description

Improve existing asphaltic surface by asphalt wedging and installing new asphalt pavement.

Project Status

Planned for 2019.

Traffic Impacts

Highway will remain open with daytime flagging operations during construction.

More Information

Capital Improvement Program

 

 

 

 

JJ

CTH N to STH 55

Town of Vandenbroek

Project Description

The highway is in need of wider paved lanes, paved shoulders, and flatter ditch slopes to meet current County highway design and safety standards. A roundabout is being designed at the intersection with CTH N. A multi-use trail is also being considered on the south side of the highway.

Project Status

Project is in design phase.  Right-of-way acquisition planned for 2020. Reconstruction is planned as early as 2021.

Traffic Impacts

A 4-way stop has been installed at the CTH N & CTH JJ intersection, and will remain until the intersection is reconstructed as a roundabout.

More Information

Capital Improvement Program

County JJ Webpage

 

 

KK

John Street to CTH N

Appleton

Project Description

This project is a traffic engineering study, design, and construction to improve capacity and operations of the existing system.  The project may include traffic signal upgrades and minor geometric changes to accommodate traffic. This project includes a cost share with the City of Appleton and Calumet County.

Project Status

In study phase.

Traffic Impacts

Pending. 

More Information

Capital Improvement Program

 

 

 

KK

& N Intersection

Buchanan/Calumet County

Project Description

Based on the CTH KK study, a northbound right turn lane is recommended at the CTH N & CTH KK intersection.

Project Status

Construction is planned for 2019.

Traffic Impacts

Northbound traffic may be restricted to 1 lane of traffic during daily construction activities.

More Information

Capital Improvement Program

 

 

 

KK

John Street to STH 441

City of Appleton

Project Description

Concrete pavement repairs and an eastbound auxiliary lane between Kensington Drive and STH 441 interchange to increase capacity of the highway.

Project Status

Planned in Summer 2019

Traffic Impacts

County KK / Calumet Street will be restricted to 1 lane in each direction. Access to properties along the roadway will be coordinated by the contractor. Driveway access will be limited when concrete repairs are needed in front of driveways.

More Information

Capital Improvement Program

 

 

 

M

STH 15 to Olk St

Hortonville

Project Description

Improve asphaltic surface by profile milling and installing a new asphalt overlay. 

Project Status

Planned in 2019. 

Traffic Impacts

Highway will remain open with daytime flagging operations during construction.

More Information

Capital Improvement Program

 

N

CTH KK to CTH CE

Buchanan/Calumet County

Project Description

The highway is in need of reconstruction to meet today’s highway standards.  The project will include a center turn lane between CTH KK to Emons/Buchanan Rd to allow thru traffic to bypass left turning vehicles at driveways and intersections. The roundabout at Emons/Buchanan Rd will be expanded to accommodate increased traffic volumes.  Traffic signals will be installed at the CTH CE ramp intersections.

Project Status

Project is in design phase.  Right-of-way acquisition may be in 2020. Roadway Reconstruction may be as early as 2021.

Traffic Impacts

The Highway will be closed to thru traffic during construction. The detour is expected to be County KK, Highway 55, and County CE.

More Information

Capital Improvement Program

 

 

 

N

Maes Avenue to Highway 96

Kimberly and Little Chute

Project Description

Concrete pavement repairs for pavement, and possible deck sealing for the bridge over the Fox River.

Project Status

Planned for 2019

Traffic Impacts

Traffic will be reduced to 1 lane in each direction along County N during the project

More Information

Capital Improvement Program

 

 

 

OO

& French Road Intersection

Grand Chute, Little Chute

Project Description

Study and design intersection improvements. Intersection options may include signalization or restricting certain traffic movements.  The long term need and use of French Road between Highway 96 and County J will also be studied.

Project Status

Study to start in 2019.

Traffic Impacts

TBD

More Information

Capital Improvement Program

 

 

 

 

 

OO

I-41 to Mason Street

Grand Chute, Appleton

Project Description

Improve existing asphaltic surface by profile milling and paving an asphalt overlay urban sections and pulverizing, reshaping the stone base and full depth paving on rural sections.

Project Status

Planned for 2019.

Traffic Impacts

County OO may be closed to traffic between County A (Lynndale Dr) and Mason St.  It will remain open to a minimum of 1 lane in each direction between I-41 and County A.  The detour is expected to be I-41 and Highway 47 (Richmond St).

More Information

Capital Improvement Program

 

 

 

U

I-41 to STH S

Town of Oneida, Brown County

Project Description

Design & reconstruct to current rural county standards, with wider lanes, paved shoulders and flatter ditch slopes.

Project Status

Project is in the design phase. Right-of-way acquisition is expected to begin in 2019.

Construction proposed as early as 2021.

Traffic Impacts

Highway will be closed to through traffic.  Detour expected to be I-41 and CTH S.

More Information

Capital Improvement Program

 

 

Future Highway Projects

For future year projects, check out the Highway portion of the Outagamie County Capital Improvement Program.

 

Wisconsin Department of Transportation

For information on state and US highway projects in Outagamie County, contact the Wisconsin Department of Transportation or click on their website pages linked here:

WisDOT Northeast Region Weekly Project Updates

WisDOT Northeast Region Highway Projects and Studies

WIS 15 Expansion - US 45 - Lily of the Valley Dr.