County Highway Construction and Paving Project Updates as of 06/20/2019

A

Mayflower Rd to WIS 47

Towns of Black Creek & Bovina

Project Description

The highway is in need of wider paved lanes, paved shoulders, and flatter ditch slopes to meet current County highway design and safety standards.

Project Status

Peters Concrete is expected to start reconstruction the first week of July and completion is anticipated early October, 2019.

   

7/8 week’s work:  Road was Closed and Detour was set up on Monday July 8.  Temporary Erosion Control items (Silt Fence, Rock Bags, Culvert Pipe Checks) were installed on the project.  Roadway Signs (except Stop Signs) were removed from the project. Excavation and grading of new subgrade started ¼ mile West of STH 47 and continued to the West.

7/15 work)Excavation and grading of new subgrade to continue working west to Hample Road.  Driveway culverts between Hample Road and ¼ mile West of STH 47 could occur, if culvert pipes are delivered to the project.

Traffic Impacts

Highway will be closed to through traffic.  Detour will be WIS 76 and CTH S.

More Information

Capital Improvement Program

CTH A Webpage

 

A

WIS 76 to Mayflower Rd

Towns of Black Creek & Bovina

Project Description

The highway is in need of wider paved lanes, paved shoulders, and flatter ditch slopes to meet current County highway design and safety standards.

Project Status

WIS 76 to Mayflower Rd – Construction planned for 2020

Traffic Impacts

Highway will be closed to through traffic.  Detour planned to be Hwy 76 and CTH S.

More Information

Capital Improvement Program

CTH A Webpage

 

 

A

(see OO too)

CTH OO to Capitol Drive

Town of Grand Chute

Project Description

Improve existing asphaltic surface by profile milling and installing a new asphalt overlay in conjunction with CTH OO between I-41 and Mason Street.

Project Status

Repaving planned for July 2019.

Traffic Impacts

Highway will be restricted to 1 lane in each direction when milling and paving is taking place.  There will be intersection closures during the work day.   A detour route will be established.

More Information

Capital Improvement Program

 

 

CA

CTH CB to Mall Drive

Towns of Grand Chute & Greenville

Project Description

The highway will be reconstructed as a 4-lane divided urban highway with curb & gutter on both the median shoulder and outside shoulder.  Multi-lane Roundabouts are planned at the intersections of Mayflower Drive and at McCarthy Road to improve operations and safety. A multi-use trail will be constructed on the north side of the highway, and sidewalks and pedestrian crossings of CTH CA are planned at the roundabouts.

Project Status

Right-of-way acquisition is complete. 

Utility relocation in 2019.

Reconstruction in 2020.

Traffic Impacts

Portions of the highway will be closed during construction. The signed detour route will be I-41, Highway 96, and County CB.  Construction planned for 2020.

More Information

Capital Improvement Program

CTH CA Webpage

 

 

CB

& Atlantis Intersection (north of CTH CA)

Town of Greenville

Project Description

Construct a multi-lane roundabout at the intersection of County CB & Atlantis Drive.  Also realign Discovery Drive intersection to Atlantis Drive.

Project Status

Construction planned to start as early as July 29, 2019 and be complete the end of October, 2019.

Traffic Impacts

Project will be built in two phases.  Phase 1 will be the internal airport street network for Discovery Drive and Atlantis Drive.  Phase 2 will be the County CB & Atlantis intersection. County CB will be closed to through traffic during Phase 2.  The signed detour for County CB will be County CA, I-41, and Highway 96.

More Information

Capital Improvement Program

CTH CB Webpage

 

 

CE

& Railroad Street Intersection

Village of Kimberly

Project Description

Traffic study, design, and future reconstruction of the intersection. Several alternatives are being considered, including traffic signals, roundabout and unique alternatives that have restrictions to cross traffic.

Project Status

Conceptual alternatives were presented to Kimberly Planning Commission in December 2018.  Preliminary plans and a full public informational meeting is planned in Spring 2019.  Reconstruction may be as early as 2021.

Traffic Impacts

Pending

More Information

County CE & Railroad Street Webpage

 

 

CE

& CTH N Interchange Improvements

Town of Buchanan

Project Description

Traffic signals will be installed at both ramp intersections.

Project Status

Planned to start the week of June 17, 2019 and be operational early August, 2019.

Traffic Impacts

County N will be reduced to 1 lane in each direction during project work.  Daytime closures of the westbound off ramp may be required during portions of the project.  The southern ramp intersection will be an all-way stop during the project. 

More Information

Capital Improvement Program

 

 

 

CE

and CTH K (Buchanan Rd) Intersection

Town of Buchanan

Project Description

Study and design of intersection improvements

Project Status

The median was closed to cross traffic in May 2018.  The Highway Dept has been studying the impacts the median closure has on safety and operations.  No new operational issues have been discovered at key adjacent intersections.

The County continues to work with the Village of Combined Locks and Town of Buchanan regarding the future of the intersection.  The speed limit along County CE is also being studied.

Traffic Impacts

County CE Traffic can make a right turn onto Buchanan Road, and Buchanan Road traffic can make a right turn onto County CE.  All Buchanan Road cross movements are restricted.

More Information

Capital Improvement Program

 

 

 

CE

WIS 55 to CTH Q

City of Kaukauna

Project Description

Improve existing asphaltic surface by pulverizing existing pavement, regrading stone base and installing a new asphalt surface. Spot improvements are planned for traffic operations and safety.

Project Status

Repaving planned for 2020.

Traffic Impacts

The highway will be closed to through traffic. The signed detour route will likely be Highway 55, County KK, and County D in Brown County

More Information

Capital Improvement Program

 

 

 

CE

CTH Q to Haas Rd

Town of Buchanan, City of Kaukauna

Project Description

Improve existing asphaltic surface by pulverizing existing pavement, regrading stone base and installing a new asphalt surface. Spot improvements are planned for traffic operations and safety.  An extension of the CE Trail is planned.

Project Status

Construction planned for 2020.

Traffic Impacts

The highway will be closed to through traffic. The signed detour route will likely be Highway 55, County KK, and County D in Brown County

More Information

Capital Improvement Program

 

 

 

CE

Haas Rd to Outagamie Rd

Town of Buchanan

Project Description

Improve existing asphaltic surface by pulverizing existing pavement, regrading stone base and installing a new asphalt surface.

Project Status

Repaving planned to start in August, 2019.

Traffic Impacts

The highway will be closed to through traffic. The signed detour route will likely be Highway 55, County KK, and County D (Brown County).

More Information

Capital Improvement Program

 

 

 

EE

(Ballard Rd)

CTH O to CTH S

Towns of Center and Freedom

Project Description

Improve existing asphaltic surface by pulverizing the pavement, regrading the stone base, and paving a new asphaltic surface

Project Status

Culvert pipe replacement and ditching is ongoing.  Paving is anticipated to start mid-July and anticipated to be completed early August, 2019.

Traffic Impacts

Highway will be closed to through traffic.  Detour expected to be County O, County C, and County S.

More Information

Capital Improvement Program

 

 

 

GV

and McCarthy Rd Intersection

Grand Chute

Project Description

Construction of a roundabout at the CTH GV intersection and reconstruction of McCarthy Road between Brookview Drive through the CTH GV intersection.

Project Status

Utility relocations are ongoing.  Construction is scheduled to start June 17, 2019 and is anticipated to be complete October, 2019. 

Traffic Impacts

County GV and McCarthy Rd will be closed to traffic. Detour expected to be Highway 96 and County CB.

More Information

Capital Improvement Program

 

 

 

JJ

CTH N to WIS 55

Town of Vandenbroek

Project Description

The highway is in need of wider paved lanes, paved shoulders, and flatter ditch slopes to meet current County highway design and safety standards. A roundabout is being designed at the intersection with CTH N. A multi-use trail is also being considered on the south side of the highway.

Project Status

Project is in design phase.  Right-of-way acquisition planned for 2020. Reconstruction is planned as early as 2021.

Traffic Impacts

A 4-way stop has been installed at the CTH N & CTH JJ intersection, and will remain until the intersection is reconstructed as a roundabout.

More Information

Capital Improvement Program

County JJ Webpage

 

 

KK

John Street to CTH N

Appleton

Project Description

This project is a traffic engineering study, design, and construction to improve capacity and operations of the existing system.  The project may include traffic signal upgrades and minor geometric changes to accommodate traffic. This project includes a cost share with the City of Appleton and Calumet County.

Project Status

In study phase.

Traffic Impacts

Pending. 

More Information

Capital Improvement Program

 

 

 

KK

& N Intersection

Buchanan/Calumet County

Project Description

Based on the CTH KK study, a northbound right turn lane is recommended at the CTH N & CTH KK intersection.

Project Status

Construction is planned for 2020.

Traffic Impacts

Northbound traffic may be restricted to 1 lane of traffic during daily construction activities.

More Information

Capital Improvement Program

 

 

 

KK

John Street to WIS 441

City of Appleton

Project Description

Concrete pavement repairs and an eastbound auxiliary lane between Kensington Drive and WIS 441 interchange to increase capacity of the highway.

Project Status

Vinton Construction is expected to start repairs June 17 and is expected to be completed by August 16, 2019.

Traffic Impacts

County KK / Calumet Street will be restricted to 1 lane in each direction. Access to properties along the roadway will be coordinated by the contractor. Driveway access will be limited when concrete repairs are needed in front of driveways.

More Information

Capital Improvement Program

County KK Website

 

 

M

WIS 15 to Olk St

Hortonville

Project Description

Improve asphaltic surface by profile milling and installing a new asphalt overlay. 

Project Status

The project will start as early as July 1 and is expected to be complete in late July, 2019. 

Traffic Impacts

Highway will be closed to through traffic and a detour established on Olk Street and WIS 15.

More Information

Capital Improvement Program

 

 

 

N

CTH KK to CTH CE

Buchanan/Calumet County

Project Description

The highway is in need of reconstruction to meet today’s highway standards.  The project will include a center turn lane between CTH KK to Emons/Buchanan Rd to allow thru traffic to bypass left turning vehicles at driveways and intersections. The roundabout at Emons/Buchanan Rd will be expanded to accommodate increased traffic volumes.  Traffic signals will be installed at the CTH CE ramp intersections.

Project Status

Project is in design phase.  Right-of-way acquisition may be in 2020. Roadway Reconstruction may be as early as 2023.

Traffic Impacts

The Highway will be closed to thru traffic during construction. The detour is expected to be County KK, Highway 55, and County CE.

More Information

Capital Improvement Program

 

 

 

N

Maes Avenue to Highway 96

Kimberly and Little Chute

Project Description

Concrete pavement repairs for pavement, and possible deck sealing for the bridge over the Fox River.

Project Status

Planned to start as early as July 1, 2019 and be complete in early August, 2019.

Traffic Impacts

Traffic will be reduced to 1 lane in each direction along County N during the project

More Information

Capital Improvement Program

 

 

 

OO

& French Road Intersection

Grand Chute, Little Chute

Project Description

Study and design intersection improvements. Intersection options may include signalization or restricting certain traffic movements.  The long term need and use of French Road between Highway 96 and County J will also be studied.

Project Status

Study to start in 2019.

Traffic Impacts

TBD

More Information

Capital Improvement Program

 

 

 

OO

(See A also)

I-41 to Mason Street

Grand Chute, Appleton

Project Description

Improve existing asphaltic surface by profile milling and paving an asphalt overlay urban sections and pulverizing, reshaping the stone base and full depth paving on rural sections. Stage 1 will close CTH OO between CTH A and Mason Street.  Planned to start June 17, 2019.  Stage 2 will include lane closures between I-41 and CTH A, planned to start July 1, 2019.

Project Status

The project will have 2 stages.  Total project completion is anticipated to be early August, 2019. 

Traffic Impacts

County OO will be closed to traffic between County A (Lynndale Dr) and Mason St.  It will remain open to a minimum of 1 lane in each direction between I-41 and County A.  At times there will be restrictions at A & OO intersection and a detour route will be established and signed.  Stage 1 detour is A, JJ, WIS 47. 

More Information

Capital Improvement Program

 

 

 

U

I-41 to WIS S

Town of Oneida, Brown County

Project Description

Design & reconstruct to current rural county standards, with wider lanes, paved shoulders and flatter ditch slopes.

Project Status

Project is in the design phase. Right-of-way acquisition is expected to be acquired in 2019.

Construction proposed as early as 2021.

Traffic Impacts

Highway will be closed to through traffic.  Detour expected to be I-41 and CTH S.

More Information

Capital Improvement Program

County U Website

 

Future Highway Projects

For future year projects, check out the Highway portion of the Outagamie County Capital Improvement Program.

 

Wisconsin Department of Transportation

For information on state and US highway projects in Outagamie County, contact the Wisconsin Department of Transportation or click on their website pages linked here:

WisDOT Northeast Region Weekly Project Updates

WisDOT Northeast Region Highway Projects and Studies

WIS 15 Expansion - US 45 - Lily of the Valley Dr.