County N is currently closed to traffic for Phase 2 watermain replacment and scheduled to re-open in late August.
|
N |
CTH KK to CTH CE Town of Buchanan |
|
Project Description |
This project is for design, right-of-way, and ultimate reconstruction of this segment of County N. A 3-lane urbanized pavement section is planned as well as expanding the existing Emons/Buchanan Rd roundabout in order to improve capacity. Federal funding has been awarded through the STP-Urban program. |
|
Project Status |
Right-of-way acquisition and utility coordination are currently ongoing. Utility relocations are currently scheduled throughout 2024and 2025with roadway reconstruction rescheduled for 2026. |
|
Traffic Impacts |
County N closed to traffic in late July to allow for Phase 2 of watermain reconstruction. Local and emergency access is being maintained. A signed detour is in place and utilizes County KK, WIS 441, and County CE. County N is currently scheduled to reopen to traffic in late August. |
|
Design Engineer |
Westwood Infrastructure |
Project Schedule
Design - 2022 and ongoing
Right-of-Way Acquisition – 2023 and ongoing
Utility Relocation – 2024 and 2025
Roadway reconstruction - 2026
Preliminary Construction Plans -
Right of Way Plat REVISED 06 30 2023
PIM # 3 Public Involvement Meeting Information (August 2023)
Buchanan Trail & Sidewalk Action Plan
|
PIM #2 Public Involvement Meeting Information (February 2022) PIM Zoom Recording Access Passcode: 9i&DXgTi |
PIM #1 Public Involvement Meeting Information (July 2018)
For more information please contact:
highwayemail@outagamie.org
or
920-832-5673