County Highway Project Updates as of 07/23/2014

CB/BB

CTH CB (CTH BB to Spencer Street) & CTH BB at CTH CB

Towns of Greenville, Grand Chute, and Winnebago County - Town of Menesha.

Project Description

This project is for construction of pavement widening and traffic signal upgrades to the intersection of CTH CB & CTH BB and to improve the existing asphaltic surface by installing a new asphalt overlay.

Project Status

Scheduled for the 2014 construction season.

Traffic Impacts

Both highways will remain open to traffic, but will have lane closures with flaggers.

More Information

The intersection has been experiencing a high rate of crashes for several years. Additional lanes will be added to provide safer sight lines for turning traffic, and provide a better level of service through the intersection. This project includes a cost share with Winnebago County. See the Capital Improvement Program, pages 45 & 46.

 

 

CE/N

CTH CE at CTH N

Town of Buchanan

Project Description

Erosion is exposing underground utilities, undermining a culvert end wall, and threatening stability of the highway ramp. The project will realign Garners creek, re-grade and stabilize the slope failure, install riprap protection.

Project Status

Scheduled for the 2014 construction season.

Traffic Impacts

Highway will remain open with shoulder closures only.

More Information

See the Capital Improvement Program, page 48.

 

 

DD

CTH DD (USH 45 to CTH D)

City of New London & Town of Maple Creek

Project Description

Project will reclaim existing pavement and install new asphalt pavement.

Project Status

Scheduled for the 2014 construction season.

Traffic Impacts

The highway will remain open to traffic with lane closures and flaggers. Motorists should expect delays and loose gravel.

More Information

See the Capital Improvement Program, page 51.

 

 

E

CTH E (Columbia Ave to STH 55)

Town of Freedom

Project Description

This is not a county project, but does affect county highways.  This project is a Freedom Sanitary District project to complete utility work.  It is scheduled to start May 5 and is expected to be completed by August 1. 

Traffic Impacts

The project is permitted to close CTH S and CTH E with detours posted. 

More Information

Contact the Freedom Sanitary District for more information 788-5763

 

 

G

CTH G (STH 55 to CTH Y)

City of Seymour & Towns of Seymour & Oneida

Project Description

The proposed project is to improve the existing asphaltic surface by reclaiming and installing new asphalt pavement. The City of Seymour will be urbanizing the segment between Mainline Dr and Independence Dr by installing curb, gutter, and storm sewer prior to paving.

Project Status

Construction is in progress and is expected to be completed by mid September.

Traffic Impacts

Starting July 28, the road will be closed to thru traffic with a detour posted using STH 55, STH 54, and CTH Y.

More Information

See the Capital Improvement Program, pages 55 & 56.

 

GV

CTH GV (Silver Spring Rd to CTH CB)

Towns of Grand Chute & Greenville

Project Description

The proposed project is to improve the existing asphaltic surface by milling the asphalt, rubblizing the underlying concrete, and installing a new asphalt pavement with 4' paved shoulders.

Project Status

Construction has been completed.

Traffic Impacts

The road is now open.

More Information

See the Capital Improvement Program, page 57.

 

 

N

CTH N (Buchanan Rd to E 3rd St)

Village of Kimberly and Town of Buchanan

Project Description

The proposed project is to improve the existing asphaltic surface by profile milling and installing a new asphalt overlay for this segment of urban highway. Improvements are also proposed at the Kennedy Ave intersection.

Project Status

Construction is in progress and is expected to be completed around July 31.

Traffic Impacts

During June 18-20, the road will be closed at the CN railroad crossing south of E. 3rd St. Canadian National Railways will be making repairs to the railroad crossing. A detour will be posted using CTH CE, STH 441, and CTH OO.

 

Otherwise, the road will remain open to traffic with lane closures and flaggers. Expect delays.

More Information

See the Capital Improvement Program, page 67.

 

 

N

CTH N (CTH OO to Maple St)

Village of Little of Chute

Project Description

The proposed project is to improve the existing asphaltic surface by installing a new asphalt overlay for this segment. From CTH OO to Elm St, the pavement markings will be reconfigured from four thru lanes to two thru lanes with a two-way-left-turn lane to improve traffic flow and safety.

Project Status

Construction is in progress and is expected to be completed around July 31.

Traffic Impacts

Road will remain open to traffic with lane closures and flaggers. Expect delays.

More Information

See the Capital Improvement Program, page 69.

 

 

S

CTH S (Mallard Lane to CTH E)

Town of Freedom

Project Description

This is not a county project, but does affect county highways.  This project is a Freedom Sanitary District project to complete utility work.  It is scheduled to start May 5 and is expected to be completed by August 1. 

Traffic Impacts

The project is permitted to close CTH S and CTH E with detours posted. 

More Information

o    Contact the Freedom Sanitary District for more information 788-5763

 

S

CTH S (STH 76 to Kelly Rd)

Town of Ellington

Project Description

The proposed project is to reconstruct the rural highway to meet current design standards, including 4-ft paved shoulders and flatter ditch slopes. Horizontal curves will be reconstructed to meet 55 mph travel speeds.

Project Status

Construction is in progress and is expected to be completed around September 30.

Traffic Impacts

The road will be closed to thru traffic starting Tuesday, May 27 with a detour posted using STH 76, CTH A, STH 47.

More Information

The existing roadway experiences a tremendous amount of heavy truck traffic resulting in expedited deterioration. The existing roadway does not meet current design standards and will be reconstructed to meet current standards for safety. See the Capital Improvement Program, page 72.

 

T

CTH T (STH 96 to STH 15)

Towns of Dale and Hortonia

Project Description

The proposed project is to improve the existing asphaltic surface by making spot base repairs and installing a new asphalt overlay for this segment of highway.

Project Status

Scheduled for the 2014 construction season.

Traffic Impacts

Road will remain open to traffic with lane closures and flaggers. Expect delays.

More Information

See the Capital Improvement Program, page 73.

 

2015-2018 Highway Projects

For future year projects, check out the Highway portion of the Outagamie County 2014-2018 Capital Improvement Program.

 

Wisconsin Department of Transportation