County ZZ & Haas Rd Project Updates

Print
Press Enter to show all options, press Tab go to next option

County ZZ (Z to Brown County Line) & Haas Rd (Z to ZZ)

Updates made 10/12/2017 - Please check back often. Updates may be made on a frequent basis.

Construction Schedule:
Year  Highway   Segment  
 2017  County ZZ  County Z to a point just northeast of Eagle Road  
 2017  Haas Road  County Z to County ZZ  
 2018  County ZZ  Just northeast of Eagle Road to East County Line  
Project Location:  Town of Buchanan

Project information - The project includes:
• Reconstruction of County Road ZZ to improve the overall safety of the highway.
• Widen travel lanes from 11 to 12 feet.
• Widen shoulders from 3 to 6 feet.
• Horizontal curves will be “straightened” to meet design criteria for the posted 55 MPH speed limit.
• Vertical curves will be “flattened” at spot locations to improve sight distance and meet design criteria for the 55 MPH speed limit.
• The existing section of County ZZ from County Z to Haas Road will be realigned onto Haas Road. The existing intersection of County Z and County ZZ will be eliminated.
• The intersection of County ZZ with County GG and New Road will be realigned to improve safety and traffic operations.
• Right turn lanes will be added at the intersections of County Z with Haas Road and the intersection of County ZZ with County GG.
• Existing bridge structure over the un-named tributary to the Fox River will be replaced with a large culvert pipe. This will accommodate the wider roadway and improve drainage.
• All intersections will be widened to improve traffic operations.

The project is scheduled to be constructed in two phases. The first phase will begin in 2017 and includes the section from County Z to Andrea Lane. The remainder of the project, Andrea Lane to Outagamie Road, will be constructed in 2018.
Traffic control
The roadway will be closed to through traffic. Local traffic will be allowed access to property and businesses along County ZZ.

Right of Way
Additional right of way is required for this project. A continuous strip of land acquisition will be required on both sides of the roadway throughout the project limits. Property owners where right of way will be required will be contacted later this year.

 

Transportation Project Plat

Staking: McMahon Associates, 1445 McMahon Drive, Neenah, WI
Phone: 920-751-4200 Email: MKohlbeck@mcmgrp.com
The stakes will show new right of way acquisition areas. Please do not disturb the stakes until after the Negotiator has visited with property owners in the area.

Appraiser: Steiro Appraisal Service, Inc., 2244 Fox Heights Lane, Green Bay, WI
Phone: 920-497-1849  Email: hbenike@steiroappraisal.com
Proposed Plan as of November 17, 2016
Public Involvement/More Details
January 27, 2016 Public Informational Meeting:
Notice

• Preliminary Maps as of 1/28/2016:

  1. Page 1
  2. Page 2 
  3. Page 3
  4. Page 4
  5. Page 5
  6. Page 6
  7. Page 7
  8. GIS Interactive Exhibit Map

Please mail any written comments to andy.rowell@outagamie.org

For more information, please contact:

Andy Rowell, P.E.
Highway Engineer
Outagamie County Highway Department
1313 Holland Road
Appleton, WI 54915
(920)832-5673
Email: Andy.Rowell@outagamie.org

Mike Kohlbeck, P.E.
Project Engineer
McMAHON
1445 McMahon Drive
Neenah, WI 54956
(920)751-4200
Email: mkohlbeck@mcmgrp.com