Real Estate Appraiser hired for this project:
 Ann Davis, MAI, CGA
 CORRE, Inc.
 608-826-6155
 adavis@correinc.com

 Proposed Preliminary Right of Way Plats

STH 76 to Mayflower Road Plat - 6/19/17

2017/18 - Right of Way acquisition process expected to start in fall 2017

2020 - Construction expected to start

Mayflower Road to STH 47 Plat - 12/11/17

2017 - Right of Way acquisition process expected to start in June

2019 - Construction expected to start

Proposed Preliminary Construction Plans

STH 76 to Mayflower Road - 5/17/17

Mayflower Road to STH 47 - 5/23/17

 
Engineering design continues for the two projects on County A. Plans as of January 2017 are below:
Scheduled for reconstruction as early as 2019.

Public Informational Meeting - Held on June 22, 2016

 

Proposed Detour Plan

 